Update received January 2024
External painting is nearing completion with Scaffolding due to be removed in the next week. Upon the removal of the scaffolding the Chours works will be able to be completed and Gib delivered for lining to commence. The vehicle crossing has been poured just prior to Christmas and in addition to this Watercare has installed the bulk water meter. EACC has been issued from Auckland Council, with plans to lodge 224(c) towards the end of the month and 223(c) will commence as soon as the Gib is installed. We assess the overall completion date to be 1 June 2024, which is consistent with last month. Estimated completion for Wroughton residence is 1 June 2024.
Update received September 2023
The rear two blocks have seen significant progress with framing and truss work nearing completion, and the roofing is substantially in place.
Window installations have commenced in these blocks as well. As for the front block, construction of the ground floor is finished, and work on the second floor is well underway. We are momentarily pausing development on this block, awaiting the relocation of a power line on the property’s right side.
While Vector has scheduled this task, it’s imperative for the line to be moved before advancing to the construction of levels 2 and 3. It’s worth highlighting that despite this brief pause, our overall timeline remains unaffected, thanks to the expedited work on the rear units.
Update received Auust 2023
Framing is currently being erected and will continue over the next week. All foundational work has been successfully completed, and the project is progressing nicely.